How much does a whole house renovation cost in London?
Updated November 202612 min readBy Cristian Ghertan, Construction Director, LINX Design and Build

A full renovation of a London house typically costs from about £1,200 to over £3,200 per m² of floor area, depending on how much is stripped out and the finish. For a 110 m² Victorian terrace that is roughly £140,000 to £240,000 for a full modernisation, before any extension or loft.
Cost per m² by level of work
| Level of work | What it usually means | London guide per m² |
|---|---|---|
| Light | Decoration, flooring, some joinery, new kitchen or bathroom | £800 to £1,200 |
| Medium | New kitchen and bathrooms, partial rewire, new heating, replastering | £1,200 to £2,000 |
| Structural | Strip out, full rewire and replumb, structural openings, new roof coverings | £2,000 to £3,200 or more |
These are planning stage budgets from Hampstead Renovations (reviewed 23 March 2026), which also gives £140,000 to £240,000 for a 110 m² Victorian terrace and £320,000 to £650,000 or more for a large period house with structural openings and a premium fit out. BestBuilders (updated 7 September 2026) gives a national full gut renovation of a three bed semi at £99,000 to £160,000 including VAT, and £120,000 to £225,000 in London and the South East.
Typical trade costs inside a renovation
| Item | Typical cost (three bed semi) |
|---|---|
| Full rewire | £3,800 to £6,500 |
| Full replumb | £3,500 to £8,000 |
| New boiler and central heating | £4,000 to £8,000 |
| Reroof | £6,500 to £14,500 |
Figures are from BestBuilders (September 2026), including VAT. On a London period house, add replastering, sash window repairs, damp and timber treatment, floor levelling and structural repairs found once the house is stripped back.


Fees and costs often left out
- Design and engineering. Architect, structural engineer and, on bigger jobs, a services designer.
- Building control. Rewiring, new heating, structural openings and replacement windows all fall under building regulations.
- Party wall notices if you cut into or underpin a shared wall.
- Planning or listed building consent where you change the outside or the house is listed. See our guide to listed building consent basics.
- Temporary accommodation and storage. A full strip out is rarely livable.
- Contingency. Hampstead Renovations and other London guides suggest 10 to 15%, more for older or heavily altered houses.
VAT on renovation work
Most renovation work to an occupied home is charged at 20%. Two exceptions are worth checking. A house empty for two years or more can qualify for the reduced 5% rate on renovation work under HMRC rules. Many energy saving installations, such as insulation, heat pumps and solar panels, are zero rated until 31 March 2027 when fitted by a professional (FMB, June 2026). The Boiler Upgrade Scheme also offers up to £7,500 toward a qualifying heat pump. This is general information, not tax advice. See our guide to VAT on building work.
How long does a whole house renovation take?
BestBuilders gives 4 to 8 weeks for a light refresh, 3 to 5 months for a medium renovation and 6 to 12 months for a full gut renovation, plus 4 to 12 weeks up front if planning is needed.
What drives cost up or down
- Condition. Old wiring, lead pipes, failed render, rot and subsidence are only fully known once the house is opened up.
- Layout changes. Each new opening in a load bearing wall needs a steel and engineer's design.
- Period features. Restoring cornicing, sash windows and original floors costs more than replacing them, but often adds more value.
- Energy upgrades. Insulation, a heat pump and new windows add cost now but cut running costs. See our guide to fitting a heat pump during a renovation.
- Specification. Kitchens, bathrooms and joinery can double the fit out budget on their own.
What to budget before you build: fees and pre build costs
Before anyone lifts a tool you will pay for design, approvals and checks. These are the published 2026 figures we use when helping clients set a budget. See our guide to architect, engineer and other fees: what to budget before you build for the full breakdown.
| Item | Typical 2026 cost | Source |
|---|---|---|
| Architect, planning drawings only | £1,000 to £2,500 (single storey extension), £2,000 to £3,500 (two storey), £900 to £1,500 (loft) | HomeOwners Alliance, updated Jan 2026 |
| Architect, full service | 3% to 15% of the construction cost, depending on size, complexity and involvement | HomeOwners Alliance, updated Jan 2026 |
| Structural engineer, loft or extension package | £750 to £2,200 | HomeOwners Alliance, Jan 2026 |
| Householder planning application | £548 (from 1 April 2026) | GOV.UK planning fees |
| Lawful development certificate (proposed) | £274 | GOV.UK planning fees |
| Building control, council example | £1,003 (extension up to 20 m²), £1,320 (20 to 60 m² or a loft up to 60 m²), £1,583 (60 to 100 m²), all including VAT | Redbridge Council schedule, 1 April 2026 |
| Party wall surveyors | About £700 to £1,200 for one agreed surveyor; about £1,500 to £4,000 per neighbour in London with two surveyors | Bookabuilder, Jun 2026 |
Building control fees vary by council and by approver, so treat the Redbridge schedule as a guide only. Redbridge also lets extensions built at the same time be added together to set the fee band. Other pre build items to allow for are a measured survey of the existing house, SAP energy calculations, a Thames Water build over agreement if you build near a public sewer, and specialist reports such as trees or drainage. All are quoted per project.
Extension, loft and full renovation together: a worked London budget
Doing all three in one project is common in London, and it is usually cheaper than three separate jobs because you pay for one set of scaffolding, one strip out and one programme. Here is how published 2026 figures add up for a typical 110 m² Victorian terrace with a 14 m² side return and a rear dormer loft.
| Element | Published London range | Basis and source |
|---|---|---|
| Full renovation of the existing house, 110 m² | £140,000 to £240,000 | Hampstead Renovations, Mar 2026 |
| Kitchen side return, 14 m² | £62,000 to £82,000 | Before VAT, BestBuilders, Aug 2026 |
| Rear dormer loft | £58,000 to £82,000 | Before VAT and fees, Hampstead Renovations, Mar 2026 |
| Hip to gable loft, if the house is semi detached | £72,000 to £98,000 | Before VAT and fees, Hampstead Renovations, Mar 2026 |
| Building work subtotal (terrace with dormer) | about £260,000 to £404,000 | Sum of the three rows above |
On top of that subtotal, add professional fees from the table above, a contingency of 10 to 15% (more for an older or heavily altered house), and VAT at 20% on any figure quoted before VAT. A two storey side extension on a semi detached house costs more than a side return; see our guide to two storey extension cost in London. For the order of work, see our guide to extension, loft and full renovation together: cost and order of work in London.
Renovating a smaller three bedroom house
BestBuilders (September 2026) puts a full gut renovation of a three bedroom semi at £120,000 to £225,000 including VAT in London and the South East. Using the London per m² bands above, a 90 m² house works out at roughly £72,000 to £108,000 for a light refurbishment, £108,000 to £180,000 for a medium one and £180,000 to £288,000 for a structural renovation.
Buying a doer upper: how to budget
- Survey before you commit. Reallymoving's August 2026 average for a London Level 2 survey was £590 and a Level 3 survey costs about £630 to £1,500 (HomeOwners Alliance, October 2026). A specialist damp report typically costs £150 to £300.
- Price the works from the survey. Use the per m² bands above, choose the level of work honestly, and get a builder to walk the house before exchange.
- Add fees and approvals from the pre build table.
- Add a contingency at the top of the 10 to 15% range for an unmodernised period house, because condition is only fully known once it is opened up.
- Check the VAT position. A house empty for two years or more can qualify for the reduced 5% rate on renovation work under HMRC rules.
- Use the numbers in the negotiation. Your offer is subject to contract until exchange, so you can share survey extracts and repair quotes with the agent and revise your offer (HomeOwners Alliance, July 2026).
Our guide to buying a house that needs work in London: surveys, budgets and what to offer covers this in more depth.
When costs start spiralling: how to regain control
- Pause new decisions and get a cost to complete. Ask your builder or project manager for a written list of work done, work committed and work still to come, with prices.
- Separate the causes. Hidden defects found on opening up, changes you asked for, and provisional sums that were too low each need a different answer. BestBuilders (August 2026) notes that drainage diversion or deeper foundations found after digging typically add £1,000 to £6,000.
- Value engineer what is not yet ordered. Kitchens, glazing, joinery and finishes are where most savings can still be made without touching the structure.
- Phase the rest. Finish the structure, roof and services now, and leave decoration, landscaping or a second bathroom for later.
- Check your contract. A fixed price for a defined scope should only change through agreed variations. If extras are appearing without written agreement, raise it straight away and in writing.
- Do not stop paying without a contractual reason. Withholding money outside the contract terms can put you in breach. Take advice if relations break down; see our guide to when things go wrong with a builder: extra costs, disputes and insolvency.
Frequently asked questions
Can I live in the house during a full renovation?
For a full strip out, usually not. For a phased renovation, many families stay, with work done floor by floor.
Should I renovate and extend at the same time?
Usually yes. One set of scaffolding, one programme and one contract cost less than two separate projects. See our guide to renovating a Victorian or Edwardian house in London.
How do I stop the budget running away?
Get a detailed scope of works, fix the specification before you start, keep a 10 to 15% contingency and agree every change in writing. Read our guide to variations on building projects.
Is it cheaper to buy a renovated house?
Sometimes. Our guide to whether to extend or move compares the real costs in London.
How much should I budget for pre build costs on a renovation and extension?
Allow for design, engineering, approvals and surveys, which on a typical London extension and renovation add up to several thousand pounds before any building starts. Published 2026 figures include £1,000 to £3,500 for architect planning drawings (or 3% to 15% of build cost for a full service), £750 to £2,200 for a structural engineer, £548 for a householder planning application, about £1,000 to £1,600 for council building control in an example London borough, and £700 to £4,000 or more per neighbour for party wall surveyors.
Our renovation costs are spiralling out of control. What can we do?
Pause new decisions, get a written cost to complete, and sort the overspend into hidden defects, your own changes and underestimated provisional sums. Then value engineer items not yet ordered, such as the kitchen, glazing and finishes, phase non essential work, and insist that every further change is priced and agreed in writing before it is done. Keep paying what the contract says is due unless you have a contractual reason not to.
How much does an extension and loft conversion cost together?
In London, expect the two together to cost roughly the sum of each, less some savings on scaffolding and preliminaries. Published 2026 figures put a 14 m² side return at £62,000 to £82,000 before VAT and a rear dormer at £58,000 to £82,000 before VAT and fees, so about £120,000 to £164,000 of building work before VAT, fees and contingency.
What is a realistic budget for a full renovation, side extension and loft conversion in London?
For a typical 110 m² Victorian terrace, published 2026 figures add up to about £260,000 to £404,000 of building work before VAT, fees and contingency. Add professional fees, a 10 to 15% contingency and VAT where figures exclude it. A semi detached house with a hip to gable loft or a two storey side extension will cost more.
What does it cost to renovate a Victorian terrace in south west London?
A full renovation of a 110 m² Victorian terrace is about £140,000 to £240,000 on a 2026 London guide, before any extension or loft. Add a side return and a dormer loft and the building work rises to about £260,000 to £404,000 before VAT, fees and contingency. Many south west London streets are in conservation areas, which can affect windows, roofs and front gardens.
How much does it cost to renovate a small three bedroom house in London?
BestBuilders (September 2026) puts a full gut renovation of a three bedroom semi at £120,000 to £225,000 including VAT in London and the South East. A lighter refresh of a 90 m² house is closer to £72,000 to £108,000 using 2026 London per m² bands.
How much should I budget for a doer upper?
Budget the purchase price and stamp duty, then the works at £800 to £3,200 or more per m² depending on how much needs doing, plus fees, a contingency at the top of the 10 to 15% range and VAT. Get a Level 2 or Level 3 survey first (about £590 for a London Level 2 in August 2026), price the works before exchange, and use the quotes to negotiate.