Cost Guides
Kitchen extension cost in London: build, kitchen and glazing
Updated November 20267 min readBy Cristian Ghertan, Construction Director, LINX Design and Build

A kitchen extension in London is really three budgets: the building work, the kitchen itself and the glazing. For a 30 m² single storey kitchen extension, expect roughly £83,000 to £134,000 for the build before VAT in London, plus £10,000 to £50,000 or more for the kitchen, depending on what you choose.
Budget 1: the building work
| Specification | National per m² (before VAT) | London guide per m² (before VAT) |
|---|---|---|
| Standard | £2,200 to £2,500 | About £2,750 to £3,375 |
| Good | £2,500 to £2,900 | About £3,125 to £3,915 |
| Excellent | £2,900 to £3,300 | About £3,625 to £4,455 |
Figures are from Homebuilding and Renovating (updated 19 February 2026), with their 25 to 35% London premium applied. In their mid range 30 m² example the main items were foundations and floor slab £19,500, external walls and roof £26,000, structural alterations £6,000, plumbing and heating £5,500, electrics £5,000, plastering and decoration £4,200, flooring £3,800 and lighting £2,500. For extension types see our guides to rear extension cost, side return extension cost and wraparound extension cost in London.
Budget 2: the kitchen
| Kitchen level | Typical cost | Source |
|---|---|---|
| Flat pack, 8 to 16 cabinets | £3,300 to £9,100 | Homebuilding and Renovating, Mar 2026 |
| Mid range | £10,000 to £20,000 | Homebuilding and Renovating, Mar 2026 |
| Trade kitchen with quartz worktops | £14,000 to £19,000 | BestBuilders, 2026 |
| Bespoke joinery with stone | £28,000 to £55,000 | BestBuilders, 2026 |
| Luxury, including all related work | £40,000 to £100,000 | Homebuilding and Renovating, Mar 2026 |
Which? (April 2026) says fitting labour is usually about 20 to 30% of the kitchen spend, and quotes Magnet suggesting around 30% of the budget goes on plumbing, flooring, electrics and other items that are not in the cabinet price. Appliances, worktops and the extractor are often where budgets slip. LINX Square, our group company, supplies tiles, flooring, sanitaryware and heating products, which can help keep these items on budget.


Budget 3: the glazing
- A 4m folding door, fitted: £6,500 to £9,500 (BestBuilders, 2026).
- A 3m by 2m roof lantern: £3,800 to £5,200.
- Frameless structural glazing: £10,000 to £25,000 extra over standard doors.
- Homebuilding and Renovating's 30 m² example allowed £14,500 for windows and doors.
Glass also affects the rest of the design. Large areas of glazing can mean a bigger steel, solar gain to manage and extra insulation elsewhere to meet building regulations. LINX Glass, our group company, can price glazing in house. See our guide to rooflights, sliding doors and glazing for extensions.
Fees, approvals and VAT
- Fees. Homebuilding and Renovating allows £9,300 to £13,800 for professional fees and admin on its 30 m² example, including architect, structural engineer, building control and party wall costs.
- Planning. Many single storey rear kitchen extensions are permitted development: up to 3m deep on a terrace or semi detached house, or 4m detached, and 6m or 8m under prior approval. Prior approval costs £249 and a householder application £548 from 1 April 2026.
- Thames Water. A build over agreement is needed if you build within 3m of a public sewer.
- VAT at 20% on the build and on the kitchen if it is supplied and fitted by a VAT registered firm.
How long does it take?
The kitchen is fitted in the last few weeks of the build, so order it early enough that it arrives on time. BestBuilders (2026) gives 12 to 20 weeks on site for a side return kitchen extension and 14 to 18 weeks for a wraparound. See our guide to how long an extension takes.
Ways to keep the total down
- Keep the extension a simple rectangle with a flat roof.
- Use standard door and window sizes rather than oversized panels.
- Keep the sink and cooker near existing drains and gas.
- Choose the kitchen before the build price is fixed, so services go in the right place first time.
- Get a fixed price scope of works that says clearly who supplies and fits the kitchen.
Getting the kitchen layout right in an extension
The layout should be fixed before the build price is, because it decides where drains, gas, extract ducting, power and steel go. Which? (April 2026) gives practical dimensions to plan around:
| Rule of thumb | Dimension (Which?, Apr 2026) |
|---|---|
| Work triangle: sink, hob and fridge | Each side no longer than about 1.2m |
| Space between parallel runs or an island and a run | At least 120cm so two people can pass |
| Clearance in front of an open unit door | 40cm to the nearest opposite unit |
| Worktop to wall cupboards | At least 40cm |
| Typical worktop height | 90cm, adjusted to your elbow height |
| Narrow rooms | Under 180cm wall to wall, consider 50cm deep units |
- Choose a shape for the room. An L shape with an island suits most rear extensions; a galley suits a long side return; a U or G shape gives most storage.
- Keep wet areas near the drains. Sinks and dishwashers close to the soil stack avoid long runs under the new floor.
- Plan extraction early. Building regulations require kitchen extract of 30 l/s through a cooker hood or 60 l/s elsewhere. An island hob needs a route for ducting.
- Zone the space. Separate cooking, dining and sitting areas, with the dining table nearest the garden doors.
- Put power and lighting on the drawings. Which? found too few sockets was one of the most common kitchen design regrets. Plan task lighting over worktops.
- Utility and pantry. A separate utility keeps the washing machine noise out of the open plan space; a WC must not open directly into the kitchen.
- Our guide, Kitchen extension layouts that work in London houses, shows typical layouts for terraces and semis.
Frequently asked questions
Is the kitchen included in an extension quote?
Often not. Many quotes cover the build to plastered and floor screeded finish, with the kitchen supplied by you or a kitchen company. Check the scope line by line. Read our guide to how to compare builder quotes like for like.
Can I keep a kitchen during the build?
Usually a temporary kitchen can be set up in another room. The old kitchen is taken out when the rear wall is opened.
How much should I spend on the kitchen?
There is no fixed rule. Many owners spend more on the kitchen in a large open plan extension because it is the main living space.
Do I need underfloor heating?
Not always, but it suits large glazed rooms with limited wall space. See our guide to underfloor heating in extensions.
Can you help with my kitchen extension layout?
Yes. As a design and build contractor, we look at the layout with you at the free site visit and feasibility assessment, and the agreed layout is fixed in the scope of works before the price, so drains, extraction, power and steel go in the right place first time. As a starting point, keep the sink, hob and fridge within about 1.2m of each other, allow at least 120cm between an island and the run opposite (Which?, April 2026), and keep the sink near the existing drains.